Prince William Water is committed to providing reliable water service to its customers today and far into the future. Our ability to provide drinking water and wastewater services for homes, businesses, schools and public facilities throughout much of Prince William County requires a robust infrastructure network.

Each year, Prince William Water adopts a planning document called the Capital Improvement Program (CIP). The CIP identifies projects across a five-year horizon, with a focus on preserving and enhancing Prince William Water’s water and sewer infrastructure.

Our interactive map (linked below) identifies some CIP projects with significant community impact that are currently in the design and construction phases. The map also identifies some projects managed by others – such as the Virginia Department of Transportation, Prince William County and developers – in which Prince William Water system improvements are within the scope of their work. Please click the button below to launch the interactive map.

You can review the full CIP document, which identifies all CIP projects in the current five-year plan.

Current and Future CIP Construction Projects

The Capital Improvement Program (CIP) is a five-year plan outlining key construction projects that are necessary to upgrade and maintain Prince William Water's water and wastewater systems.

CIP Map - Key Projects

Highlighted Projects

We are committed to ongoing investment in our infrastructure and operations to ensure that we can continue to provide clean, safe, and refreshing water to our community. If you have any questions or concerns about our capital projects, please don’t hesitate to contact us.

Bull Run Mountain Well Upgrades

The Bull Run Mountain Well Upgrades Project is to improve the drinking water supply available to its current and potential future customers residing within our area of service on Bull Run Mountain and at Evergreen.  This includes customers who live in Bull Run Mountain Estates and near Evergreen Country Club.

Engineering and hydrogeological analyses began in early 2019. Construction of new wells and piping that will be required to connect these wells to our distribution system is expected to start in 2026 with a one- to two-year schedule for completion.

  • Improve the well system to ensure adequate water supply, which may involve rehabilitation of existing wells and/or construction of new wells; and
  • Enhance the quality of the water delivered to our customers.
Project Status:
In Design
A small octagonal building in the woods

Heritage Hunt Sewage Pumping Station Replacement and Force Main

The existing Heritage Hunt Sewage Pumping Station (SPS) will be replaced to increase pumping capacity from 3.6 million gallons per day (MGD) to 7.81 MGD. The new, higher-capacity SPS will be capable of serving the anticipated build-out of residential and commercial developments in and around the Heritage Hunt community. A new 24-inch Force Main will be constructed from the SPS to a location at the corner of Heathcote Boulevard and Route 29.

Project Status:
Under Construction
Rendering of new Heritage Hunt Sewage Pumping Station

H.L. Mooney Advanced Water Reclamation Facility-Wide Improvements

Prince William Water’s award-winning H.L. Mooney Advanced Water Reclamation Facility (AWRF) in Woodbridge treats up to 24 million gallons of wastewater daily, meeting or exceeding federal and state standards. After treatment at Mooney AWRF, the reclaimed wastewater is released into Neabsco Creek, a tributary of the Potomac River. 

This infrastructure project is designed to improve operational resiliency and service levels, provide additional odor control, and allow the plant to continue meeting regulatory requirements. Project elements include enhancements to several areas of the Mooney facility: primary clarifier odor control upgrade; primary clarifier collection system improvements; primary clarifier electrical improvements; equalization basin modifications; Return Activated Sludge Building pump modifications; additional Ultraviolet equipment; yard valves replacement; supplemental carbon system improvements; alkalinity system upgrades; ferric system improvements; secondary clarifier improvements; plant structural protection and refurbishment.

Project Status:
Under Construction
Aerial View of H.L. Mooney Advanced Water Reclamation Facility

Ridge Road Water Storage Tank Replacement Project

The T16 Ridge Road Water Storage Tank Replacement Project is part of Prince William Water’s ongoing commitment to maintain and strengthen the reliability of drinking water infrastructure across the service area. The existing T16 tank, located at 1860 Ridge Road in Haymarket, VA, is a 96,000-gallon bolted steel ground storage tank constructed in 1994. After more than 30 years of service, the tank has reached the end of its useful life and shows extensive structural degradation, coating failure, and multiple safety and regulatory deficiencies. 

Following comprehensive inspections and engineering evaluations, Prince William Water determined that replacement of the existing tank with a new welded steel tank is the most cost-effective and long-term solution. A welded steel tank offers an expected service life of approximately 75 years, improved structural resilience, lower lifecycle maintenance, and full compliance with updated AWWA and OSHA standards. 

The project also includes construction of a new access road, grading improvements, safety enhancements, replacements of aging electrical and instrumentation systems, and upgrades to on-site operational equipment. Together, these improvements ensure continued reliable water service to the surrounding communities and improved operational efficiency for decades to come.

Why Replacement Is Recommended

Engineering analysis showed that rehabilitating the existing tank would require extensive repairs, long outages, and costs approaching or exceeding that of a new tank, while only adding 10–15 years of life. In contrast, a new welded steel tank provides:

  • Longer service life (~75 years)
  • Lower long-term maintenance costs
  • Enhanced structural integrity
  • Improved access and safety
  • Reduced outage duration compared to rehabilitation

Schedule

  • Design Duration: Approximately 10 months (including shop drawings, fabrication, and submittals).
  • Construction Duration: Approximately 10 months, including demolition, foundation work, tank erection, coating, and commissioning.
Project Status:
In Design
A large, aged water tank.

Route 1 Water Main Replacement Project

This project consists of the replacement of a water transmission main along Route 1 from the Garfield Booster Station (near the intersection of Route 1 and Neabsco Road) running south toward Fuller Heights Road. The purpose of this project is to increase transmission capacity from the Garfield Booster Station to southern portions of the Dumfries Pressure Zone, to improve system reliability and to meet customer demand.

Project Status:
Under Construction
A backhoe and an employee in safety gear performing work on a street

Occoquan Creek Sewage Pumping Station (SPS) Replacement and Gravity Sewer Main Project

The Occoquan Creek Sewage Pumping Station (SPS) Replacement and Gravity Sewer Main Project will modernize critical wastewater infrastructure serving Prince William County. The existing pump station, built in 1975, has aging equipment and is increasingly vulnerable to flooding and shoreline erosion. A 2018 condition assessment confirmed the need for full replacement to ensure long-term reliability, environmental protection, and continued service to the community.

The project also includes construction of a new 42-inch gravity sewer main that will convey wastewater more efficiently to the new pump station. The gravity main will replace aging infrastructure, improve system hydraulics, and provide capacity for future growth.

Prince William Water evaluated multiple locations and selected a new pump station site that improves safety, efficiency, and resiliency while minimizing community impacts. The new facility will be elevated above the floodplain and relocated away from the shoreline, significantly reducing flood risk. Construction is targeted to begin in late 2026, with an estimated one- to two-year schedule.

Project Goals

  • Replace the existing Occoquan Creek SPS with a modern facility that meets current design and regulatory standards.
  • Construct a new 42-inch gravity sewer main to improve conveyance reliability and system performance.
  • Increase future wastewater capacity to approximately 17.28 million gallons per day (MGD).
  • Improve system resiliency by reducing flood risk and exposure to shoreline erosion.
  • Minimize odor and noise impacts through advanced odor control and sound-reducing enclosures.

Key Benefits

  • A more resilient, discreet, and reliable wastewater facility.
  • Improved wastewater conveyance through a new large-diameter gravity sewer main.
  • Activated carbon odor control achieving up to 99.5% hydrogen sulfide removal.
  • Reduced odor formation due to improved pump efficiency and lower wastewater retention times.
  • Reliable wastewater service to support current demands and future growth in Prince William County.
Project Status:
In Design
A small brick building surrounded by chain link fence

Occoquan River Crossing Project

The Occoquan River Crossing Project is a collaboration between three providers of drinking water: Fairfax Water, Prince William Water, and Virginia American Water. This project consists of designing and constructing two new 42-inch parallel water mains that will cross under the Occoquan River inside a 400-foot-long tunnel and connect to existing water mains on the Prince William County side of the river. In addition, a new water main will be installed to connect Fairfax Water’s Griffith Water Treatment Plant (located in Fairfax County) with the 42-inch water mains at the Occoquan River.

This project also includes the installation of a new drinking water pump at the Griffith Plant and two interconnections between existing water mains in Prince William County: one at Tanyard Hill Road and the other at the Horner Road Commuter Parking Lot (alternate location: Lake Ridge).

The engineering design, design schedule, construction schedule, and construction process are being managed by Fairfax Water, with coordination among the three utilities.

Project Status:
Under Construction
Aerial view of Occoquan Dam

Spinnaker Court Sewage Pumping Station, L02 and Force Main

The existing Spinnaker Court Sewage Pumping Station (SPS), constructed in 1970, as a wet well/dry well station will be replaced to upgrade the SPS to the latest codes and standards, and replace the aging structures and equipment. Five hundred feet of new six-inch force main will also be constructed to replace the aging four-inch force main discharging from the SPS to a manhole at Helm Court. The new station will serve the community for many years.

Project Status:
Under Construction
Photo: a small building made of green painted bricks in the woods

Completed Projects

We are committed to ongoing investment in our infrastructure and operations to ensure that we can continue to provide clean, safe, and refreshing water to our community. If you have any questions or concerns about our capital projects, please don’t hesitate to contact us.

Graham Park Sewage Pumping Station Project

Replacement of an existing antiquated Sewage Pumping Station (SPS) and force main (FM), and raise the SPS control building and equipment above the 100-year flood plain elevation. 

Project Status:
Completed
Graham Park Sewage Pumping Station

Montclair/Four Seasons Water System Improvements

The Montclair/Four Seasons Water System Improvements Project provides improved reliability to Montclair, Four Seasons, Brittany, and Southlake, as well as commercial areas and neighborhoods along Dumfries Road. The project's three main components include a Booster Pumping Station, Supply Main, and Discharge Mains.

Project Status:
Completed
Montclair Four Seasons project rendering

Occoquan Forest Sewage Pumping Stations 36 and 37 Replacement

Replacement of existing antiquated sewage pumping stations and cast iron force mains to continue providing sewer service to this community. The Occoquan Forest Sewage Pumping Stations were constructed in the early 1970s. The project will reduce maintenance expenses, provide new emergency backup power supplies, and improve safety conditions at the sewage pumping stations.

Project Status:
Completed
Occoquan Forest Sewage Pumping Station Entrance