Occoquan Forest Sewage Pumping Stations 36 and 37 Replacement
- Project Status:
- Under Construction
- Webpage Updated:
- Dec 13, 2024
Project Description
Replacement of existing antiquated sewage pumping stations and cast iron force mains to continue providing sewer service to this community. The Occoquan Forest Sewage Pumping Stations were constructed in the early 1970s. The project will reduce maintenance expenses, provide new emergency backup power supplies, and improve safety conditions at the sewage pumping stations.
Project Information
Project Start Date | spring 2018 |
Construction Start Date | spring 2021 |
Estimated Completion Date | winter 2025 |
Current Project Activities
-
1
Site improvements and paving are ongoing.
Additional Information
-
Occoquan Forest Project Summary
Occoquan Forest Project Summary -
Occoquan Forest Project FAQs - Updated 7.5.2024
Occoquan Forest Project FAQs - Updated 7.5.2024 -
Occoquan Forest Project Exhibit
Occoquan Forest Project Exhibit -
3.2.2021 - Occoquan Forest Owners Association Presentation
3.2.2021 - Occoquan Forest Owners Association Presentation -
4.29.18 Occoquan Forest Community Meeting
4.29.18 Occoquan Forest Community Meeting