Occoquan River Crossing Project
- Project Status:
- Under Construction
- Webpage Updated:
- Dec 02, 2024
Project Description
The Occoquan River Crossing Project is a collaboration between three providers of drinking water: Fairfax Water, Prince William Water, and Virginia American Water. This project consists of designing and constructing two new 42-inch parallel water mains that will cross under the Occoquan River inside a 400-foot-long tunnel and connect to existing water mains on the Prince William County side of the river. In addition, a new water main will be installed to connect Fairfax Water’s Griffith Water Treatment Plant (located in Fairfax County) with the 42-inch water mains at the Occoquan River.
This project also includes the installation of a new drinking water pump at the Griffith Plant and two interconnections between existing water mains in Prince William County: one at Tanyard Hill Road and the other at the Horner Road Commuter Parking Lot.
The engineering design, design schedule, construction schedule, and construction process are being managed by Fairfax Water, with coordination among the three utilities.
Project Information
Project Start Date | summer 2022 |
Construction Start Date | summer 2022 |
Estimated Completion Date | spring 2025 |
Current Project Activities
-
1
36-inch water line Shutdown and Tie-in was completed successfully.
Image Gallery
Additional Information
-
Occoquan River Crossing Project Summary
Occoquan River Crossing Project Summary -
Occoquan River Crossing Project FAQs - Updated 7.5.2024
Occoquan River Crossing Project FAQs - Updated 7.5.2024 -
Traffic Management Plan
Traffic Management Plan -
Pedestrian Management Plan (April 2023)
Pedestrian Management Plan (April 2023) -
Safety Info Tunnel Process (April 2023)
Safety Info Tunnel Process (April 2023) -
Town Hall Presentation 3.24.2021
Town Hall Presentation 3.24.2021 -
Project Presentation (Nov. 2020)
Project Presentation (Nov. 2020)