Occoquan River Crossing Project
- Project Status:
- Under Construction
- Webpage Updated:
- May 06, 2025
Project Description
The Occoquan River Crossing Project is a collaboration between three providers of drinking water: Fairfax Water, Prince William Water, and Virginia American Water. This project consists of designing and constructing two new 42-inch parallel water mains that will cross under the Occoquan River inside a 400-foot-long tunnel and connect to existing water mains on the Prince William County side of the river. In addition, a new water main will be installed to connect Fairfax Water’s Griffith Water Treatment Plant (located in Fairfax County) with the 42-inch water mains at the Occoquan River.
This project also includes the installation of a new drinking water pump at the Griffith Plant and two interconnections between existing water mains in Prince William County: one at Tanyard Hill Road and the other at the Horner Road Commuter Parking Lot (alternate location: Lake Ridge).
The engineering design, design schedule, construction schedule, and construction process are being managed by Fairfax Water, with coordination among the three utilities.
Project Information
Project Start Date | summer 2022 |
Construction Start Date | winter 2022 |
Estimated Completion Date | winter 2026 |
Current Project Activities
-
1
Design coordination for the Lake Ridge Interconnection in progress.
Image Gallery
Additional Information
-
Occoquan River Crossing Project Summary - 070524.pdf
Occoquan River Crossing Project Summary - 070524.pdf -
Occoquan River Crossing FAQs -070524.pdf
Occoquan River Crossing FAQs -070524.pdf -
Traffic Management Plan
Traffic Management Plan -
Pedestrian Management Plan (April 2023)
Pedestrian Management Plan (April 2023) -
Safety Info Tunnel Process (April 2023)
Safety Info Tunnel Process (April 2023) -
Town Hall Presentation 3.24.2021
Town Hall Presentation 3.24.2021 -
Project Presentation (Nov. 2020)
Project Presentation (Nov. 2020)