Heritage Hunt Sewage Pumping Station Replacement and Force Main
- Project Status:
- Under Construction
- Webpage Updated:
- Jan 08, 2025
Project Description
The existing Heritage Hunt Sewage Pumping Station (SPS) will be replaced to increase pumping capacity from 3.6 million gallons per day (MGD) to 7.81 MGD. The new, higher-capacity SPS will be capable of serving the anticipated build-out of residential and commercial developments in and around the Heritage Hunt community. A new 24-inch Force Main will be constructed from the SPS to a location at the corner of Heathcote Boulevard and Route 29.
Project Information
Project Start Date | summer 2020 |
Construction Start Date | summer 2022 |
Estimated Completion Date | spring 2025 |
Current Project Activities
The design, permitting, and advertisement for bids occurred from July 2020 through January 2022. The bid opening for the construction contract was on February 15, 2022. The Board of Directors approved the construction contract award on April 14, 2022. Construction began in August 2022; the estimated final completion is Spring 2025.
-
1
Construction of the new pumping station is complete.
-
2
The contractor is currently working on startup and testing activities at the pumping station. Once successfully tested, the existing pumping station will be demolished and the final restoration of the property will be completed.
-
3
Contractor repaving of impacted areas of Heritage Hunt Drive with temporary asphalt is complete. The Heritage Hunt HOA will repave the full width of Heritage Hunt Drive, Fieldstone Way, and Alderwood Way after the project is complete.
Project Documents
-
Heritage Hunt Project Summary
Heritage Hunt Project Summary -
2024.07.01 Heritage Hunt SPS and FM FAQs_0.pdf
2024.07.01 Heritage Hunt SPS and FM FAQs_0.pdf -
Community Outreach Q&A 05.11.22
Community Outreach Q&A 05.11.22 -
Presentation: Community Outreach 05.11.22
Presentation: Community Outreach 05.11.22 -
Heritage Hunt Historical Documents
Heritage Hunt Historical Documents