Project Description

The existing Heritage Hunt Sewage Pumping Station (SPS) will be replaced to increase pumping capacity from 3.6 million gallons per day (MGD) to 7.81 MGD. The new, higher-capacity SPS will be capable of serving the anticipated build-out of residential and commercial developments in and around the Heritage Hunt community. A new 24-inch Force Main will be constructed from the SPS to a location at the corner of Heathcote Boulevard and Route 29.

Project Information

Project Start Date summer 2020
Construction Start Date summer 2022
Estimated Completion Date spring 2025

Current Project Activities

The design, permitting, and advertisement for bids occurred from July 2020 through January 2022. The bid opening for the construction contract was on February 15, 2022. The Board of Directors approved the construction contract award on April 14, 2022. Construction began in August 2022; the estimated final completion is Spring 2025.

  • 1

    Construction of the new pumping station is complete.

  • 2

    The contractor is currently working on startup and testing activities at the pumping station. Once successfully tested, the existing pumping station will be demolished and the final restoration of the property will be completed.

  • 3

    Contractor repaving of impacted areas of Heritage Hunt Drive with temporary asphalt is complete. The Heritage Hunt HOA will repave the full width of Heritage Hunt Drive, Fieldstone Way, and Alderwood Way after the project is complete.