Project Description

The existing Spinnaker Court Sewage Pumping Station (SPS), constructed in 1970, as a wet well/dry well station will be replaced to upgrade the SPS to the latest codes and standards, and replace the aging structures and equipment. Five hundred feet of new six-inch force main will also be constructed to replace the aging four-inch force main discharging from the SPS to a manhole at Helm Court. The new station will serve the community for many years.

Project Information

Project Start Date summer 2024
Construction Start Date summer 2024
Estimated Completion Date summer 2026

Current Project Activities

The information shown reflects the current progress of the project.

  • 1

    The design, permitting and advertisement for bids occurred from June 2021-April 2024. 

  • 2

    The bid opening for the construction contract was on April 25, 2024.

  • 3

    The Board of Directors approved the construction contract award on June 13, 2024.

  • 4

    Construction is anticipated to begin in September 2024 and the estimated final completion is June 2026.

Project Documents