Spinnaker Court Sewage Pumping Station, L02 and Force Main
- Project Status:
- Under Construction
- Webpage Updated:
- Feb 25, 2026
Project Description
The existing Spinnaker Court Sewage Pumping Station (SPS), constructed in 1970 as a wet well/dry well station, will be replaced to upgrade the SPS to the latest codes and standards as well as replace the aging structures and equipment. Five hundred feet of new six-inch force main will also be constructed to replace the aging four-inch force main discharging from the SPS to a manhole at Helm Court. The new station will serve the community for many years.
Project Information
| Project Start Date | summer 2024 |
| Construction Start Date | summer 2024 |
| Estimated Completion Date | summer 2026 |
Current Project Activities
The information shown reflects the current progress of the project.
-
1
The design, permitting and advertisement for bids occurred from June 2021-April 2024.
-
2
The bid opening for the construction contract was on April 25, 2024.
-
3
The Board of Directors approved the construction contract award on June 13, 2024.
-
4
The Notice to Proceed (NTP) for the construction contract was issued on September 3, 2024. The estimated final completion is June 2026.
-
5
The contractor started clearing the trees and bushes along the new force main alignment in June 2025
Project Documents
-
Spinnaker Court SPS Project Summary
Spinnaker Court SPS Project Summary -
Spinnaker Court SPS FAQs
Spinnaker Court SPS FAQs
Spinnaker Ct SPS & FM Overview Presentation 2-25-25
-
Spinnaker Ct SPS and FM Overview_2-25-25.pdf
Spinnaker Ct SPS and FM Overview_2-25-25.pdf