Spinnaker Court Sewage Pumping Station, L02 and Force Main
- Project Status:
- Under Construction
- Webpage Updated:
- Dec 02, 2024
Project Description
The existing Spinnaker Court Sewage Pumping Station (SPS), constructed in 1970, as a wet well/dry well station will be replaced to upgrade the SPS to the latest codes and standards, and replace the aging structures and equipment. Five hundred feet of new six-inch force main will also be constructed to replace the aging four-inch force main discharging from the SPS to a manhole at Helm Court. The new station will serve the community for many years.
Project Information
Project Start Date | summer 2024 |
Construction Start Date | summer 2024 |
Estimated Completion Date | summer 2026 |
Current Project Activities
The information shown reflects the current progress of the project.
-
1
The design, permitting and advertisement for bids occurred from June 2021-April 2024.
-
2
The bid opening for the construction contract was on April 25, 2024.
-
3
The Board of Directors approved the construction contract award on June 13, 2024.
-
4
The Notice to Proceed (NTP) for the construction contract was issued on September 3, 2024. The actual construction activities are expected to start mid-January 2025. The estimated final completion is June 2026.
Project Documents
-
Spinnaker Court SPS Project Summary.docx
Spinnaker Court SPS Project Summary.docx -
Spinnaker Court SPS FAQ.docx
Spinnaker Court SPS FAQ.docx