Project Description

The Montclair/Four Seasons Water System Improvements Project provides improved reliability to Montclair, Four Seasons, Brittany, and Southlake, as well as commercial areas and neighborhoods along Dumfries Road. The project's three main components include a Booster Pumping Station, Supply Main, and Discharge Mains.

Project Information

Project Start Date summer 2020
Construction Start Date summer 2022
Estimated Completion Date summer 2024

Current Project Activities

  • 1

    The final design and construction phase commenced in December 2021.

  • 2

    Prince William Water’s Design-Builder (ACE/KCI) began construction activities in July 2022.

Additional Information

The information shown reflects the current progress of the project.